NTPC Green Energy Limited (NGEL) is buying LFP battery containers and grid-forming PCS for 40.58 GWh of deliverable storage, split into 7 blocks of 4.56 to 6.8 GWh. Bids close on 8 December 2026 at 15:00 IST. At 5.015 MWh per 20 ft container, the full tender needs at least 8,092 containers before any oversizing, and every bidder must either be, or partner with, a manufacturer that has already supplied 4,000 MWh of LFP containers.
On 9 November 2026, NTPC Green Energy Limited, the renewables arm of NTPC, invited bids to supply battery containers and grid-forming power conversion systems for 10 GW / 40 GWh of BESS projects. It is an international competitive bid, and the block table in the notice adds up to 40.58 GWh of deliverable capacity.
That makes it one of the largest single equipment orders for battery storage India has issued. This guide turns the notice into numbers a bidder can use: how many containers each block needs, who can qualify, how much turnover and bid security each block requires, and what to check in the container spec before 8 December.
NGEL is buying hardware and long-term service, not a finished power plant. The scope in the IFB has three parts:
The bid is single stage, two envelope: a techno-commercial bid with nil deviation, and a separate price bid. Documents are free but are only released after a bidder registers on the ETS portal and signs NGEL's non-disclosure agreement. The schedule is tight:
Timeline source: NGEL IFB, 9 Nov 2026.
Between 910 and 1,356 containers per block, using a 5.015 MWh, 20 ft container. Bidders can quote one, several or all blocks, but each block must be quoted in full, so the block is the smallest unit you can win.
| Block | Phase | Deliverable capacity (GWh) | Min. 5.015 MWh containers |
|---|---|---|---|
| B-1 | Phase 1 | 4.98 | 994 |
| B-2 | Phase 1 | 6.60 | 1,317 |
| B-3 | Phase 1 | 5.84 | 1,165 |
| B-4 | Phase 2 | 4.56 | 910 |
| B-5 | Phase 3 | 5.80 | 1,157 |
| B-6 | Phase 3 | 6.80 | 1,356 |
| B-7 | Phase 3 | 6.00 | 1,197 |
| Total | 3 phases | 40.58 | 8,092 |
Table 1. Block sizes and minimum container count. Capacity: NGEL IFB. Container count = deliverable capacity ÷ 5.015 MWh, rounded up; Jingye estimate. The block rows add to 8,096 because each block is rounded up separately.
NGEL buys deliverable capacity, while a container is rated by nameplate energy. Depth of discharge, PCS and transformer losses, and degradation over the 15-year LTSA all push the real container count above Table 1. The final oversizing must come from the technical specification in the full bidding document.
Phase 1 and Phase 3 are each roughly four times the size of Phase 2. A supplier that wins a full phase has to plan factory output and shipping for thousands of containers, not hundreds.
Figure 1. Phase capacity ÷ 5.015 MWh, rounded up. Phase capacity: NGEL IFB; container counts are a Jingye estimate.
Three more numbers give a sense of scale, all Jingye estimates at the 8,092-container minimum:
There are two ways in. Either you are a battery container manufacturer with large LFP references, or you are an Indian company with smaller BESS, solar, wind or industrial references that partners with such a manufacturer.
In practice, the partner route means most Indian EPCs and developers will bid with a container maker named in a joint undertaking. That maker shares liability for the whole contract, so choosing the partner is the single biggest decision in the bid. For background on India's wider localisation push, see our guide to the 40% local content rule under the ₹14,500 crore VGF scheme.
Average annual turnover over the last three financial years must be at least INR 69 lakh per MWh quoted. Bid security is INR 50 crore for up to 5 GWh, INR 100 crore from 5 to 10 GWh and INR 200 crore above 10 GWh.
| Block | Quoted MWh | Min. average turnover (INR crore) | Approx. USD million | Bid security (INR crore) |
|---|---|---|---|---|
| B-4 (smallest) | 4,560 | 3,146.4 | 330.6 | 50 |
| B-1 | 4,980 | 3,436.2 | 361.0 | 50 |
| B-3 | 5,840 | 4,029.6 | 423.4 | 100 |
| B-6 (largest) | 6,800 | 4,692.0 | 493.0 | 100 |
| All 7 blocks | 40,580 | 28,000.2 | 2,941.8 | 200 |
Table 2. Financial thresholds by block. Rules and bid security: NGEL IFB. Turnover = INR 69 lakh × quoted MWh; USD at the IFB's own bid-security rate (INR 50 crore = USD 5,253,200, about 95.18 INR/USD); Jingye estimate.
Two details matter. First, a bidder that cannot meet turnover alone may rely on its holding company, with a board-backed letter of support. Second, on the partner routes the qualified manufacturer must also meet the INR 69 lakh per MWh turnover test, so a partner that fits the technical clause can still fail the financial one. Net worth must also be at least 25% of paid-up share capital, with limits on erosion over the last three years.
A 10 GW / 40 GWh programme is a 4-hour design, so each 5.015 MWh container only has to deliver about 1.25 MW, roughly half the ≤ 2.5 MW rating of a typical 314Ah liquid-cooled container (Jingye estimate). The harder tests are heat, life and service. Check these before you sign a joint undertaking:
Grid-forming PCS also opens the door to black start services. See our guide to black start capability in battery energy storage systems.
It lands in a crowded month. Bidders and suppliers are pricing several large Indian programmes at once:
VGF scheme: the Union Cabinet approved INR 14,500 crore of viability gap funding for 92 GWh of storage (30 GWh of it BESS) from FY 2026-27 to FY 2030-31, with a mandatory 40% domestic content requirement for eligible BESS projects.
SECI: a 4 GW / 16 GWh standalone BESS tender in Rajasthan and Gujarat, with bids due 23 November 2026 and central financial assistance of INR 15 lakh per MWh expected.
Recent prices: the WBSEDCL 500 MW / 2,000 MWh 4-hour tender, with no VGF, was awarded in August 2026 at INR 4.35 to 4.39 lakh per MW per month.
The NGEL IFB itself does not mention a domestic content rule, so check the full bidding document rather than assuming the VGF rule applies. We covered a smaller state build-own-operate tender in our MAHAGENCO 1,600 MWh sizing guide.
Lock the partner and the block choice by the 24 November query deadline, because nothing can be clarified after that.
Our 5.015 MWh liquid-cooled BESS container is a 20 ft unit with 314Ah LFP cells, 1,331.2 V DC rated voltage (1,164.8 to 1,497.6 V), up to 2.5 MW charge and discharge power, charging from 0°C to 60°C, discharging from −30°C to 60°C and operation up to 4,000 m. It is designed to GB/T 36276, IEC/EN 62619, IEC/EN 62477, UN 38.3 and IEC/EN 63056. Our 5 MWh battery cabins already run at the Jiangsu Jingye Iron and Steel 50 MW / 100.32 MWh station (20 battery cabins with 10 × 5 MW PCS), and our liquid-cooled storage runs two cycles a day at the Huaxi Special Steel 15 MW / 30.09 MWh station. They come from a 15 GWh module and PACK line and are checked in our CNAS-accredited test lab. For NGEL bidders we can share datasheets and help convert block capacity into container counts. For India's state and VGF tenders, and for other utility-scale projects, we can quote directly.
It is an international competitive bid by NTPC Green Energy Limited, issued on 9 November 2026, to supply LFP battery containers and grid-forming PCS, supervise installation and provide 15 years of service. The block table totals 40.58 GWh of deliverable capacity.
Techno-commercial and price bids are due on 8 December 2026 at 15:00 IST. Documents can be downloaded from 12 to 23 November, and queries close at the pre-bid conference on 24 November.
No. The minimum bid is one full block, and partial-block bids are rejected. The smallest block is B-4 at 4.56 GWh and the largest is B-6 at 6.8 GWh.
Yes, if it meets one of the Indian-company routes (BESS, solar or wind, or industrial and substation references) and partners with a manufacturer that meets the 4,000 MWh Clause 1.1 test. Both must sign a joint and several undertaking.
With 5.015 MWh containers, between 910 (B-4) and 1,356 (B-6) at minimum, before oversizing for depth of discharge, losses and degradation. These are Jingye estimates; the final number depends on NGEL's technical specification.
INR 50 crore for up to 5 GWh, INR 100 crore from 5 to 10 GWh and INR 200 crore above 10 GWh. Bids without acceptable bid security are rejected.
The IFB does not state a domestic content rule. The separate VGF scheme sets 40% domestic content for eligible BESS projects, so read the full NGEL bidding document to confirm what applies here.
Send us the block you are targeting and the technical specification. We will return a container count, layout and datasheet pack for the 5.015 MWh container.
Send us your tender specHebei Jingye New Energy Technology Co., Ltd, part of Jingye Group, makes liquid-cooled BESS containers, C&I energy storage cabinets, cell contact systems, DC fast EV chargers and LFP commercial vehicle batteries for buyers worldwide.
Nov. 12, 2026
NGEL 40 GWh BESS Tender: Container Sizing, Qualification Rules and Bid Deadline (2026)
NTPC Green Energy's 10 GW / 40.58 GWh BESS tender closes on 8 December 2026 and needs at least 8,092 battery containers of 5.015 MWh. Here are the block sizes, qualification routes, turnover rules and bid steps.
Nov. 11, 2026
Brazil Tarifa Hora Certa: How Battery Storage Cuts Peak Electricity Costs from 2028
ANEEL's proposed Tarifa Hora Certa would move about 5.7 million low-voltage consumers in Brazil to time-of-use pricing from April 2028. With peak energy at R$1.73/kWh vs R$0.75 off-peak in ANEEL's Cemig example, a battery saves about R$0.90 per kWh shifted.
Nov. 10, 2026
India's new ₹14,500 crore VGF scheme backs 30 GWh of battery storage, and BESS projects must now meet a 40% domestic content rule, double the earlier 20%. Here's what it means for developers, EPCs and equipment buyers.
Let’s Get Started on Your New Energy Journey.