NGEL 40 GWh BESS Tender 2026: Containers, Rules & Deadline

NGEL 40 GWh BESS Tender: Container Sizing, Qualification Rules and Bid Deadline (2026)

Home > BLOG > NGEL 40 GWh BESS Tender: Container Sizing, Qualification Rules and Bid Deadline (2026)

NGEL 40 GWh BESS Tender: Container Sizing, Qualification Rules and Bid Deadline (2026)

Nov 12, 2026

By Daniyal, Jingye New EnergyPublished 12 Nov 202611 min read
Quick answer

NTPC Green Energy Limited (NGEL) is buying LFP battery containers and grid-forming PCS for 40.58 GWh of deliverable storage, split into 7 blocks of 4.56 to 6.8 GWh. Bids close on 8 December 2026 at 15:00 IST. At 5.015 MWh per 20 ft container, the full tender needs at least 8,092 containers before any oversizing, and every bidder must either be, or partner with, a manufacturer that has already supplied 4,000 MWh of LFP containers.

40.58GWhDeliverable capacity across 7 blocks and 3 phasesSource: NGEL IFB
8,092containersMinimum 5.015 MWh containers for the full 40.58 GWhSource: Jingye estimate
8 Dec2026Deadline for techno-commercial and price bidsSource: NGEL IFB

On 9 November 2026, NTPC Green Energy Limited, the renewables arm of NTPC, invited bids to supply battery containers and grid-forming power conversion systems for 10 GW / 40 GWh of BESS projects. It is an international competitive bid, and the block table in the notice adds up to 40.58 GWh of deliverable capacity.

That makes it one of the largest single equipment orders for battery storage India has issued. This guide turns the notice into numbers a bidder can use: how many containers each block needs, who can qualify, how much turnover and bid security each block requires, and what to check in the container spec before 8 December.

What is NGEL buying in this tender?

NGEL is buying hardware and long-term service, not a finished power plant. The scope in the IFB has three parts:

  • Supply of LFP-based containerised battery systems with grid-forming PCS.
  • Supervision of erection, installation and commissioning at each site, up to the PCS output terminals.
  • Comprehensive service and maintenance for 15 years from commissioning, under a Long Term Service Agreement (LTSA).

The bid is single stage, two envelope: a techno-commercial bid with nil deviation, and a separate price bid. Documents are free but are only released after a bidder registers on the ETS portal and signs NGEL's non-disclosure agreement. The schedule is tight:

9 Nov 2026IFB issued (No. NGEL-CS-5853-004(BESS)-9, tender search code NGEL-2026-TN000012).
12 to 23 Nov 2026Bidding documents can be downloaded from the ETS portal, after the signed NDA is uploaded.
24 Nov 2026Pre-bid conference and last date for queries. No queries are accepted after this.
8 Dec 2026, 15:00 ISTDeadline for techno-commercial and price bids.
8 Dec 2026, 15:30 ISTEnvelope I (techno-commercial) opens. Price bid opening date to be announced separately.

Timeline source: NGEL IFB, 9 Nov 2026.

How many battery containers does each block need?

Between 910 and 1,356 containers per block, using a 5.015 MWh, 20 ft container. Bidders can quote one, several or all blocks, but each block must be quoted in full, so the block is the smallest unit you can win.

Block Phase Deliverable capacity (GWh) Min. 5.015 MWh containers
B-1 Phase 1 4.98 994
B-2 Phase 1 6.60 1,317
B-3 Phase 1 5.84 1,165
B-4 Phase 2 4.56 910
B-5 Phase 3 5.80 1,157
B-6 Phase 3 6.80 1,356
B-7 Phase 3 6.00 1,197
Total 3 phases 40.58 8,092

Table 1. Block sizes and minimum container count. Capacity: NGEL IFB. Container count = deliverable capacity ÷ 5.015 MWh, rounded up; Jingye estimate. The block rows add to 8,096 because each block is rounded up separately.

These are floors, not designs

NGEL buys deliverable capacity, while a container is rated by nameplate energy. Depth of discharge, PCS and transformer losses, and degradation over the 15-year LTSA all push the real container count above Table 1. The final oversizing must come from the technical specification in the full bidding document.

How much hardware is 40.58 GWh in practice?

Phase 1 and Phase 3 are each roughly four times the size of Phase 2. A supplier that wins a full phase has to plan factory output and shipping for thousands of containers, not hundreds.

Minimum 5.015 MWh containers by phase
Phase 1 (17.42 GWh)3,474
Phase 2 (4.56 GWh)910
Phase 3 (18.60 GWh)3,709

Figure 1. Phase capacity ÷ 5.015 MWh, rounded up. Phase capacity: NGEL IFB; container counts are a Jingye estimate.

Three more numbers give a sense of scale, all Jingye estimates at the 8,092-container minimum:

  • Footprint: each 20 ft container measures 6,058 × 2,438 mm, so 8,092 containers cover about 119,500 m² (roughly 12 hectares) before spacing, roads and PCS skids.
  • Weight: at about 43 t per container, that is around 348,000 t of equipment to transport and crane into place.
  • Cells: 314Ah LFP cells averaged $54.21/kWh ex-works China in September 2026. At that price, the cells alone for 40.58 GWh cost about $2.2 billion, before containers, PCS, cooling, fire protection, freight and the LTSA.

Who can bid, and what is the partner route?

There are two ways in. Either you are a battery container manufacturer with large LFP references, or you are an Indian company with smaller BESS, solar, wind or industrial references that partners with such a manufacturer.

Route 1: qualified manufacturer (Clause 1.1)
  • Manufactured and supplied at least 4,000 MWh of containerised battery systems, in no more than 10 orders.
  • Within the last three years before techno-commercial bid opening.
  • At least one order of 500 MWh or more, supplied at a single location.
  • LFP containers only; MWh means nameplate, not output energy.
  • Reference projects need not be commissioned yet.
Route 2: Indian company with a partner
  • Indian-registered bidder with one of: 80 MWh of grid BESS containers supplied (one order ≥ 20 MWh), 80 MWh of grid BESS commissioned or supervised, 40 MWac of solar or wind, or an industrial project plus a 33 kV+ substation.
  • Must associate with a Clause 1.1 qualified manufacturer.
  • Both sign a joint and several undertaking for full contract performance.
  • Group, holding and subsidiary companies can also use these routes.

In practice, the partner route means most Indian EPCs and developers will bid with a container maker named in a joint undertaking. That maker shares liability for the whole contract, so choosing the partner is the single biggest decision in the bid. For background on India's wider localisation push, see our guide to the 40% local content rule under the ₹14,500 crore VGF scheme.

How much turnover and bid security does each block need?

Average annual turnover over the last three financial years must be at least INR 69 lakh per MWh quoted. Bid security is INR 50 crore for up to 5 GWh, INR 100 crore from 5 to 10 GWh and INR 200 crore above 10 GWh.

Block Quoted MWh Min. average turnover (INR crore) Approx. USD million Bid security (INR crore)
B-4 (smallest) 4,560 3,146.4 330.6 50
B-1 4,980 3,436.2 361.0 50
B-3 5,840 4,029.6 423.4 100
B-6 (largest) 6,800 4,692.0 493.0 100
All 7 blocks 40,580 28,000.2 2,941.8 200

Table 2. Financial thresholds by block. Rules and bid security: NGEL IFB. Turnover = INR 69 lakh × quoted MWh; USD at the IFB's own bid-security rate (INR 50 crore = USD 5,253,200, about 95.18 INR/USD); Jingye estimate.

Two details matter. First, a bidder that cannot meet turnover alone may rely on its holding company, with a board-backed letter of support. Second, on the partner routes the qualified manufacturer must also meet the INR 69 lakh per MWh turnover test, so a partner that fits the technical clause can still fail the financial one. Net worth must also be at least 25% of paid-up share capital, with limits on erosion over the last three years.

What container specs matter for a 4-hour Indian grid project?

A 10 GW / 40 GWh programme is a 4-hour design, so each 5.015 MWh container only has to deliver about 1.25 MW, roughly half the ≤ 2.5 MW rating of a typical 314Ah liquid-cooled container (Jingye estimate). The harder tests are heat, life and service. Check these before you sign a joint undertaking:

  • Chemistry and nameplate: LFP only, with nameplate MWh and deliverable MWh stated separately in the offer.
  • Heat: discharge and charge temperature range that covers Rajasthan and Gujarat summers, and liquid cooling with a stated cell temperature spread.
  • Grid-forming PCS: the PCS is part of the scope, so check that the container's DC voltage window and PCS input range match.
  • 15-year LTSA: cycle life, degradation curve and augmentation plan that hold deliverable capacity for the full service term.
  • Safety and standards: fire detection and suppression at pack, cluster and container level, plus IEC 62619 and UN 38.3 test reports.
  • Altitude and dust: derating rules for high sites and enclosure protection for desert dust.

Grid-forming PCS also opens the door to black start services. See our guide to black start capability in battery energy storage systems.

How does this tender fit with India's other storage programmes?

It lands in a crowded month. Bidders and suppliers are pricing several large Indian programmes at once:

Other live and recent Indian storage programmes

VGF scheme: the Union Cabinet approved INR 14,500 crore of viability gap funding for 92 GWh of storage (30 GWh of it BESS) from FY 2026-27 to FY 2030-31, with a mandatory 40% domestic content requirement for eligible BESS projects.
SECI: a 4 GW / 16 GWh standalone BESS tender in Rajasthan and Gujarat, with bids due 23 November 2026 and central financial assistance of INR 15 lakh per MWh expected.
Recent prices: the WBSEDCL 500 MW / 2,000 MWh 4-hour tender, with no VGF, was awarded in August 2026 at INR 4.35 to 4.39 lakh per MW per month.

The NGEL IFB itself does not mention a domestic content rule, so check the full bidding document rather than assuming the VGF rule applies. We covered a smaller state build-own-operate tender in our MAHAGENCO 1,600 MWh sizing guide.

How should bidders prepare before 8 December?

Lock the partner and the block choice by the 24 November query deadline, because nothing can be clarified after that.

  1. Register and sign NDARegister on the ETS portal before 23 November to get the documents.
  2. Pick your blocksMatch block size to the turnover you or your parent can prove, using Table 2.
  3. Confirm the partnerCheck the partner's references against Clause 1.1: 4,000 MWh, ≤ 10 orders, one 500 MWh single site.
  4. Size real MWhConvert deliverable GWh to nameplate using the spec's DoD, losses and LTSA degradation rules.
  5. Send queriesRaise spec gaps and LTSA terms before the 24 November pre-bid conference.
  6. Arrange bid securityLine up the INR 50, 100 or 200 crore bank guarantee and a physical copy for submission.
How Jingye New Energy helps

Our 5.015 MWh liquid-cooled BESS container is a 20 ft unit with 314Ah LFP cells, 1,331.2 V DC rated voltage (1,164.8 to 1,497.6 V), up to 2.5 MW charge and discharge power, charging from 0°C to 60°C, discharging from −30°C to 60°C and operation up to 4,000 m. It is designed to GB/T 36276, IEC/EN 62619, IEC/EN 62477, UN 38.3 and IEC/EN 63056. Our 5 MWh battery cabins already run at the Jiangsu Jingye Iron and Steel 50 MW / 100.32 MWh station (20 battery cabins with 10 × 5 MW PCS), and our liquid-cooled storage runs two cycles a day at the Huaxi Special Steel 15 MW / 30.09 MWh station. They come from a 15 GWh module and PACK line and are checked in our CNAS-accredited test lab. For NGEL bidders we can share datasheets and help convert block capacity into container counts. For India's state and VGF tenders, and for other utility-scale projects, we can quote directly.

Key takeaways
  • 40.58 GWh in 7 blocks: bids close 8 December 2026 at 15:00 IST, and each block must be quoted in full.
  • At least 8,092 containers of 5.015 MWh for the whole tender, before oversizing for losses and degradation (Jingye estimate).
  • Qualification hinges on the manufacturer: 4,000 MWh of LFP containers in ≤ 10 orders, one of them 500 MWh at a single site.
  • Turnover scales with MWh: INR 69 lakh per MWh means about INR 3,146 crore for the smallest block and about INR 28,000 crore for all seven.

Frequently asked questions

What is the NGEL 10 GW / 40 GWh BESS tender?

It is an international competitive bid by NTPC Green Energy Limited, issued on 9 November 2026, to supply LFP battery containers and grid-forming PCS, supervise installation and provide 15 years of service. The block table totals 40.58 GWh of deliverable capacity.

When is the bid deadline?

Techno-commercial and price bids are due on 8 December 2026 at 15:00 IST. Documents can be downloaded from 12 to 23 November, and queries close at the pre-bid conference on 24 November.

Can I bid for part of a block?

No. The minimum bid is one full block, and partial-block bids are rejected. The smallest block is B-4 at 4.56 GWh and the largest is B-6 at 6.8 GWh.

Can an Indian EPC bid without manufacturing experience?

Yes, if it meets one of the Indian-company routes (BESS, solar or wind, or industrial and substation references) and partners with a manufacturer that meets the 4,000 MWh Clause 1.1 test. Both must sign a joint and several undertaking.

How many battery containers does one block need?

With 5.015 MWh containers, between 910 (B-4) and 1,356 (B-6) at minimum, before oversizing for depth of discharge, losses and degradation. These are Jingye estimates; the final number depends on NGEL's technical specification.

How much bid security is required?

INR 50 crore for up to 5 GWh, INR 100 crore from 5 to 10 GWh and INR 200 crore above 10 GWh. Bids without acceptable bid security are rejected.

Does the tender require domestic content?

The IFB does not state a domestic content rule. The separate VGF scheme sets 40% domestic content for eligible BESS projects, so read the full NGEL bidding document to confirm what applies here.

Bidding for an NGEL block or an Indian state tender?

Send us the block you are targeting and the technical specification. We will return a container count, layout and datasheet pack for the 5.015 MWh container.

Send us your tender spec

Hebei Jingye New Energy Technology Co., Ltd, part of Jingye Group, makes liquid-cooled BESS containers, C&I energy storage cabinets, cell contact systems, DC fast EV chargers and LFP commercial vehicle batteries for buyers worldwide.

LATEST BLOGS

Let’s Get Started on Your New Energy Journey.

Copyright @Hebei Jingye New Energy Technology Co., Ltd. All Rights Reserved | sitemap.xml

+86 0311 6736 8615

+86 0755 8666 6990

Cookie Consent

This website uses cookies to improve your browsing experience, analyze site traffic, and understand where our visitors come from. By continuing to use this site, you agree to our use of cookies.