Bayernwerk 80 MWh Battery Tender: How to Size a 2026 Bid

Bayernwerk 20 MW/80 MWh Grid-Serving Battery Tender: How to Size Your Bid (2026)

Home > BLOG > Bayernwerk 20 MW/80 MWh Grid-Serving Battery Tender: How to Size Your Bid (2026)

Bayernwerk 20 MW/80 MWh Grid-Serving Battery Tender: How to Size Your Bid (2026)

Nov 16, 2026

By Daniyal, Jingye New EnergyPublished 16 Nov 20269 min read
Quick answer

Bayernwerk Netz wants a battery of 20 MW and at least 80 MWh at its Speichersdorf substation in Bavaria. It will run for the grid, under §11a EnWG, in place of a conventional grid upgrade. Registration is open from 9 to 23 November 2026, and the target is commissioning by the end of 2027. With 5.015 MWh containers, 16 units just reach 80 MWh, and 20 units give about 100 MWh with a 25% margin.

80MWhMinimum storage Bayernwerk Netz wants at Speichersdorf (20 MW)Source: TaiyangNews
240GWhBattery storage that could sit at 1,313 rural German substationsSource: Fraunhofer IEE via TaiyangNews
+91%Growth in new German battery capacity, first nine months of 2026Source: BSW-Solar via Clean Energy Wire

Germany's grid operators have started buying batteries the way they used to buy cables and transformers. On 11 November 2026, regional distribution operator Bayernwerk Netz opened an expression of interest for a 20 MW / 80 MWh battery at its Speichersdorf substation in Bavaria. The battery is meant to replace a planned conventional grid upgrade and ease congestion caused by renewable power.

The window is short: registrations close on 23 November. This article explains how grid-serving storage works, how to size an 80 MWh bid, and what to check with your battery supplier before you register.

What exactly is Bayernwerk Netz asking for?

A battery of 20 MW and at least 80 MWh, connected directly to the Speichersdorf substation and operated to meet grid needs rather than market prices. That makes it a 4-hour system (80 MWh ÷ 20 MW).

Item Detail
Issuer Bayernwerk Netz GmbH, regional distribution system operator (Bavaria)
Site Speichersdorf substation, direct connection
Size 20 MW power, at least 80 MWh energy (4 hours)
Purpose Relieve congestion, integrate more renewables, replace a conventional grid upgrade
Legal basis §11a Energiewirtschaftsgesetz (EnWG)
Storage ID BAGE_S0007
Registration 9 to 23 November 2026, open to registered service providers
Target commissioning End of 2027

Table 1. Key facts of the Speichersdorf expression of interest. Source: TaiyangNews, 11 Nov 2026.

How is a grid-serving battery different from a normal BESS?

A normal merchant battery chases price spreads. A grid-serving (netzdienlich) battery follows the grid operator's needs at one specific substation, and the operator pays for that service. Location matters: the battery only helps if it sits where the bottleneck is.

Merchant BESS
  • Earns from trading, balancing and price spreads
  • Operates on market signals
  • Can sit almost anywhere with a grid connection
  • Revenue rises and falls with the market
Grid-serving BESS (§11a EnWG)
  • Runs to relieve a named substation
  • The grid operator sets time-of-day and seasonal rules
  • Paid under a service contract with the grid operator
  • Replaces or delays a grid upgrade

Bayernwerk's first project shows how the model works. For the 5 MW pilot at Wutzldorf, the grid operator signed a service contract with MaxSolar, which operates the battery. Bayernwerk sets the time-of-day and seasonal specifications, and the battery charges at high solar output and discharges at high demand. More than 100 bidders took part in that tender.

Why are German grid operators doing this now?

Rural substations are full of solar power for a few hours a day and almost empty the rest of the time. A battery at the substation soaks up the peak and releases it later, so the existing transformer can carry much more renewable power.

A Fraunhofer IEE study for the German Solar Association looked at 1,313 rural substations. It found that smart batteries could let about 150 GW of extra PV connect with average curtailment of around 1%. That would need roughly 60 GW / 240 GWh of storage. Spread evenly, that is about 46 MW / 183 MWh per substation (Jingye estimate), more than twice the size of the Speichersdorf battery.

The market is already moving fast. Germany installed 91% more new battery capacity in the first nine months of 2026 than a year earlier, about 8.2 GWh, and large battery parks made up roughly half of it. BSW-Solar is now calling for distribution grid tenders for batteries at substations, which is exactly what Bayernwerk is running.

Jul 2025Bayernwerk Netz signs its first grid-serving storage contract with MaxSolar for Wutzldorf (5 MW).
Mar 2026N-ERGIE Netz awards its first grid-serving battery in Ansbach to MaxSolar, 20 MW / 100 MWh, against more than 20 competitors.
9 Nov 2026Bayernwerk Netz opens registration for Speichersdorf (BAGE_S0007), 20 MW / 80 MWh.
23 Nov 2026Registration closes.
End of 2027Target commissioning at Speichersdorf.

Figure 1. Grid-serving battery tenders in Bavaria. Sources: Solarserver, Bayern Innovativ, TaiyangNews.

How many battery containers does an 80 MWh bid need?

At least 16 containers of 5.015 MWh, which gives 80.24 MWh nameplate. Since the minimum is 80 MWh and every battery loses some capacity over its life, most bidders will add a margin. 20 containers (about 100 MWh) is the safer choice.

Option Containers Nameplate energy Margin over 80 MWh Power per container at 20 MW Container footprint
Minimum 16 80.24 MWh 0.3% 1.25 MW 236 m²
Moderate margin 18 90.27 MWh 12.8% 1.11 MW 266 m²
Recommended 20 100.30 MWh 25.4% 1.00 MW 295 m²

Table 2. Speichersdorf sizing with Jingye 5.015 MWh containers (6,058 × 2,438 mm, ≤ 2.5 MW each). Footprint counts the containers only, without spacing, PCS or transformers. Jingye estimate.

Power is not the limit here. Each container is rated up to 2.5 MW, so even 16 units could deliver 40 MW, twice what the site needs. Running each container at 1.0 to 1.25 MW keeps the cells at a gentle rate, which helps temperature control and lifetime.

Energy capacity options vs. the 80 MWh minimum (MWh)
Speichersdorf minimum80 MWh
16 containers80.24 MWh
18 containers90.27 MWh
Ansbach (as built)100 MWh
20 Jingye containers100.30 MWh

Figure 2. Container options compared with the tender minimum and the N-ERGIE Ansbach project (20 MW / 100 MWh). Sources: Bayern Innovativ; container options are a Jingye estimate.

The Ansbach project is a useful benchmark. N-ERGIE Netz asked for a 20 MW battery there too, and the winning project is being built at 20 MW / 100 MWh. A 20-container block lands in almost the same place.

Ask before you size

The public notice says "at least 80 MWh" but does not say whether this means nameplate energy or energy delivered at the grid connection after losses and degradation. Clarify this with Bayernwerk Netz during registration. It decides whether 16 or 20 containers is the right answer.

How should you prepare in the next seven days?

Register first, then firm up the technical package. The registration window is only two weeks, so the battery data you need for the next round should be ready before you are asked for it.

  1. Register by 23 NovRegister as a service provider for storage ID BAGE_S0007.
  2. Fix the sizeChoose 16, 18 or 20 containers once the 80 MWh definition is clear.
  3. Lock the supply chainGet datasheets, standards and a delivery slot that fits end-2027 commissioning.
  4. Plan the operationModel charging at solar peaks and discharging at demand peaks, as the grid operator sets.

When you speak to battery suppliers, these are the questions that matter for a grid-serving project:

  • Usable energy at the grid connection in year 1 and year 15, not just nameplate
  • Product standards such as IEC/EN 62619, IEC/EN 62477, IEC/EN 63056 and UN 38.3
  • Cooling method and the temperature range for charging and discharging
  • Fire protection at pack, cluster and compartment level
  • BMS and communication interfaces (Ethernet, CAN, Modbus) for the grid operator's control signals
  • Production slot, shipping time to Bavaria and on-site commissioning support
Grid code

German grid connection rules apply to the plant and its power conversion system. If you buy batteries and PCS from different suppliers, check early who provides the grid-code certificates. Our guide on all-in-one vs separate PCS systems explains the trade-offs.

How Jingye helps

A 20-container block we have already delivered

Our 5.015 MWh liquid-cooled BESS container packs 314Ah LFP cells into a standard 20 ft container (6,058 × 2,438 × 2,896 mm) at 1,331.2 V DC, rated up to 2.5 MW. It has aerosol plus water fire protection at pack, cluster and compartment level, and the product page lists GB/T 36276, IEC/EN 62619, IEC/EN 62477, UN 38.3 and IEC/EN 63056. At the Jiangsu Jingye Iron and Steel 50 MW / 100.32 MWh station we installed 20 battery cabins of 5 MWh with 10 PCS cabins of 5 MW. That is the same energy block a 100 MWh Speichersdorf bid would use.

All products come from our own 15 GWh module and PACK line with MES traceability, and they are tested in our CNAS-accredited laboratory. The company holds ISO quality, environmental and occupational health and safety management system certificates. For grid-support duty, see also our article on black start capability in BESS, or browse the full energy storage system range.

Key takeaways
  • Act this week: Speichersdorf registration (BAGE_S0007) closes on 23 November 2026.
  • It is a 4-hour system: 20 MW and at least 80 MWh, run for the grid under §11a EnWG.
  • Size with a margin: 16 containers of 5.015 MWh just meet 80 MWh; 20 give 100.3 MWh, close to the Ansbach benchmark.
  • More will follow: Fraunhofer IEE sees room for about 240 GWh of storage at rural substations.

Frequently asked questions

What is a netzdienlicher Speicher?

It is a grid-serving battery that a distribution operator uses to relieve a specific part of its network. It charges and discharges according to the grid operator's rules rather than only market prices, and is paid under a service contract.

Who can register for the Speichersdorf tender?

The expression of interest is open to registered service providers. Registration runs from 9 to 23 November 2026 under storage ID BAGE_S0007.

What does §11a EnWG allow?

Section 11a of the German Energy Industry Act lets grid operators use storage as grid-serving equipment to avoid network expansion. In Bayernwerk's tenders so far, a third party builds and operates the battery under a service contract with the grid operator.

How long must the battery store energy?

Four hours: 80 MWh at 20 MW. Bayernwerk's earlier site list required at least two hours, so this site asks for twice that.

How many 5.015 MWh containers fit an 80 MWh requirement?

Sixteen containers give 80.24 MWh nameplate. Twenty give 100.30 MWh, which leaves about 25% margin for losses and ageing (Jingye estimate).

When must the battery be running?

Bayernwerk Netz targets commissioning by the end of 2027.

Bidding for Speichersdorf or another grid-serving site?

Send us the site size and the tender notes. We will return a container layout, energy-margin calculation and datasheet pack you can use in your submission.

Get a sizing proposal

Hebei Jingye New Energy Technology Co., Ltd, part of Jingye Group, makes battery energy storage systems, C&I storage cabinets, cell contact systems and commercial vehicle batteries, from cell integration to complete containerised systems.

LATEST BLOGS

Let’s Get Started on Your New Energy Journey.

Copyright @Hebei Jingye New Energy Technology Co., Ltd. All Rights Reserved | sitemap.xml

+86 0311 6736 8615

+86 0755 8666 6990

Cookie Consent

This website uses cookies to improve your browsing experience, analyze site traffic, and understand where our visitors come from. By continuing to use this site, you agree to our use of cookies.