NTPC 40 GWh BESS Tender: How to Qualify and Size Your Bid

NTPC 40 GWh BESS Tender: How to Qualify and Size Your Block Bid (2026)

Home > BLOG > NTPC 40 GWh BESS Tender: How to Qualify and Size Your Block Bid (2026)

NTPC 40 GWh BESS Tender: How to Qualify and Size Your Block Bid (2026)

Nov 23, 2026

By Daniyal, Jingye New EnergyPublished 23 Nov 20269 min read
Quick answer

NTPC Green Energy's tender buys LFP battery containers and grid-forming PCS for 40.58 GWh of storage. It is split into seven blocks of 4.56–6.80 GWh, and you have to bid for a whole block. Bids close on 8 December 2026. To qualify as a direct supplier you need 4,000 MWh of containerised batteries supplied in the last three years. Indian EPCs and developers can also qualify by teaming with a manufacturer that meets that bar.

40.58GWhTotal deliverable capacity across 7 blocksSource: Energetica India
4,000MWhBattery containers a direct supplier must have delivered in 3 yearsSource: TaiyangNews
8,0965.015 MWh containers needed to reach 40.58 GWh on nameplateJingye estimate

On 9 November 2026, NTPC Green Energy Limited (NGEL) issued an international tender, NIT NGEL-CS-5853-004(BESS)-9. It covers containerised LFP battery systems and grid-forming power conversion systems (PCS) for a 10 GW / 40 GWh storage programme (IndianPSU). That's a big order for India. At the end of June 2026 the whole country had 9.3 GWh of battery storage installed, so this one tender is more than four times that.

This guide is for EPCs, developers and BESS integrators deciding whether to bid. It covers what the tender buys, who qualifies, what one block means in containers and money, and what to settle with your battery partner before the deadline.

What exactly is NTPC Green Energy buying?

NGEL is buying the core equipment, not complete plants. The supplier delivers LFP battery containers and grid-forming PCS. It supervises erection, installation and commissioning up to the PCS output terminals, then services and maintains the system for 15 years under a long-term service agreement (LTSA) (TaiyangNews).

10 GW against 40 GWh works out to about four hours of storage. A grid-forming PCS can set voltage and frequency itself instead of only following the grid, which is why it's becoming standard for large renewable-heavy grids.

In the supplier's scope
  • LFP containerised battery systems
  • Grid-forming PCS
  • Supervision of erection, installation and commissioning up to PCS output
  • 15-year comprehensive service and maintenance (LTSA)
Not in this package
  • Balance of plant, civil and grid works, which NGEL tenders separately (for example, the 250 MW / 1,000 MWh Kayamkulam package, which excludes containers and PCS)
  • Partial-block supply: bids below a full block are rejected

How are the 40.58 GWh split into blocks?

There are seven blocks over three phases, and the smallest one you can bid for is 4.56 GWh. You can bid for one, several or all of them. Each bid has to cover the full block capacity (Energetica India).

Table 1 turns each block into the numbers a bidder has to plan for. We counted containers using our own 5.015 MWh container. We also applied the reported turnover rule (INR 69 lakh per MWh) to each block's capacity, on the assumption that it's measured against quoted capacity. Confirm that in the tender document.

Phase / block Capacity (GWh) 5.015 MWh containers (min.) Avg. turnover needed (INR crore) Bid security (INR crore)
Phase 1, block 1 4.98 994 3,436 50
Phase 1, block 2 6.60 1,317 4,554 100
Phase 1, block 3 5.84 1,165 4,030 100
Phase 2, block 1 4.56 910 3,146 50
Phase 3, block 1 5.80 1,157 4,002 100
Phase 3, block 2 6.80 1,356 4,692 100
Phase 3, block 3 6.00 1,197 4,140 100
All 7 blocks 40.58 8,096 n/a 200 (above 10 GWh)

Table 1. Block sizes and bid security from Energetica India. Container counts and turnover figures are Jingye estimates: containers = block MWh ÷ 5.015, rounded up; turnover = block MWh × INR 0.69 crore.

Treat the container count as a floor

The tender talks about "deliverable" capacity. Usable energy at the PCS output is lower than battery nameplate once depth of discharge, conversion losses and 15 years of degradation are counted. So a real design needs more than 8,096 containers or an augmentation plan. Size against the guaranteed figure in the technical specification, not the headline GWh.

Who can qualify to bid?

There are two paths. Experienced battery container makers can bid directly. Indian companies with energy or industrial project experience can bid if they team up with a qualified battery manufacturer (Energetica India).

  1. Direct manufacturerAt least 4,000 MWh of containerised batteries in the last 3 years, in no more than 10 orders, including one order of 500 MWh or more.
  2. Indian BESS supplier80 MWh of grid-connected containerised systems supplied (one order of at least 20 MWh), plus a qualified manufacturer.
  3. Indian BESS EPC80 MWh of grid-connected BESS supplied and commissioned (one project of at least 20 MWh), plus a qualified manufacturer.
  4. Indian solar / wind EPC40 MW AC of solar or wind designed and commissioned (one plant of at least 10 MW AC), plus a qualified manufacturer.
  5. Industrial EPCOne process-industry project in 10 years plus one substation of 33 kV or above, as developer or EPC.
  6. Joint undertakingOn routes 2–4, bidder and manufacturer accept joint and several liability for the whole contract.

The money rules are steep too. Reports list average annual turnover of at least INR 69 lakh per MWh over three years, plus net-worth tests: at least 25% of paid-up capital, and not eroded by more than 30% over the last three years (Energetica India). On the smallest block, that turnover rule works out to roughly INR 3,146 crore a year (Jingye estimate). For many EPCs, the partner they pick and the balance sheet behind the bid matter more than the price.

How big is this tender for India's storage market?

It's bigger than everything India has installed so far, put together. India added 8.2 GWh of battery storage in the first half of 2026, bringing installed capacity to 9.3 GWh by the end of June (Mercom India). This one procurement is about 4.4 times that installed base.

NGEL tender vs. India's installed battery storage (GWh)
NGEL tender (Nov 2026)40.58 GWh
Installed, end June 20269.3 GWh
Added in H1 20268.2 GWh

Figure 1. Tender capacity compared with India's battery storage base. Sources: Energetica India (tender), Mercom India (installed capacity and H1 2026 additions).

For suppliers, the message is that India's buyers are moving from single projects to equipment framework buys. The winners will need container factories, PCS supply and service teams that can stay in India for 15 years.

What are the key dates?

The window is short. Reported dates (IndianPSU, Energetica India):

9 Nov 2026NIT issued on the NTPC tender portal.
12 – 23 Nov 2026Tender document sale window.
24 Nov 2026Pre-bid conference.
8 Dec 2026, 3:00 pmBid submission deadline. Techno-commercial bids open at 3:30 pm the same day.
As of 23 Nov 2026

Dates can change through corrigenda. Check the NTPC tender portal before you plan around any of them.

What should you lock down with your battery partner before 8 December?

Under routes 2–4 you carry joint and several liability with your manufacturer for the whole contract. So check your partner as hard as the client will check you.

  • Reference list adding up to 4,000 MWh of containerised systems in the last three years, in 10 orders or fewer, with one order of 500 MWh or more, and the paperwork to prove it.
  • LFP cell supply secured for the full block, with cell maker, cell size and delivery plan in writing.
  • Usable-energy guarantee at the PCS output, and how it is held over 15 years (augmentation or oversizing).
  • A grid-forming PCS that has been tested together with the battery system, not just listed as compatible.
  • A 15-year LTSA cost model: spares, site staff in India, response times, and who covers degradation.
  • Container fire protection, thermal management and monitoring that meet the tender's technical specification.

How many containers does a 4-hour block need, and at what power?

As a rough guide, a 4-hour design runs each container at about a quarter of its energy as power. Our 5.015 MWh container is rated up to 2.5 MW. At a 4-hour duration it works at about 1.25 MW, which is 5.015 MWh ÷ 4 h (Jingye estimate). That gives the PCS headroom and keeps cell stress low.

Design input What to ask for Why it matters
Usable energy at PCS output Guaranteed MWh at day 1 and in year 15 Sets the true container count
Duration 4 hours (10 GW / 40 GWh) Sets the power per container and PCS sizing
Container energy Nameplate MWh per 20 ft unit Drives land, foundations and logistics
Cycling Cycles per day from the specification Drives degradation and the LTSA cost

Table 2. Sizing inputs for a block bid. Jingye guidance; check every value against the NGEL technical specification.

How Jingye helps

Jingye New Energy makes a 5.015 MWh liquid-cooled BESS container: a standard 20 ft unit with 314Ah LFP cells, 1331.2 V DC nominal, up to 2.5 MW charge and discharge, and a three-level automatic fire suppression system. Our Jiangsu Jingye Iron and Steel 50 MW / 100.32 MWh project uses 20 sets of 5 MWh battery cabins and 10 sets of 5 MW PCS cabins. Before you name any manufacturer in an NGEL bid, including us, check its references against the 4,000 MWh rule. For India's other utility and C&I storage tenders, we're happy to share container specs and help you size the system. See more energy storage systems and project cases.

Key takeaways
  • 40.58 GWh in seven blocks: you have to bid a full block, and the smallest is 4.56 GWh.
  • 4,000 MWh track record is the bar for direct manufacturers. Indian EPCs need a partner that clears it.
  • About 900–1,360 containers per block at 5.015 MWh nameplate, and more once usable energy and degradation are counted.
  • Bids close 8 December 2026, and the reported document sale window ended on 23 November.

Frequently asked questions

What is the NTPC Green Energy 40 GWh BESS tender?

It is NGEL's international tender for LFP battery containers and grid-forming PCS for a 10 GW / 40 GWh storage programme. Total deliverable capacity is 40.58 GWh, and the supplier also provides 15 years of service and maintenance.

Can foreign battery makers bid?

Yes, it's an international competitive bid. A direct supplier must have delivered at least 4,000 MWh of containerised battery systems in the last three years. Reports don't mention local-content rules, so check the tender document.

Can I bid for part of a block?

No. The minimum bid is one complete block, and partial-block bids will be rejected. Block sizes range from 4.56 GWh to 6.80 GWh.

How much bid security is needed?

Reports list INR 50 crore for up to 5 GWh quoted, INR 100 crore for 5–10 GWh, and INR 200 crore above 10 GWh.

Why does the tender ask for grid-forming PCS?

A grid-forming PCS can set voltage and frequency itself, so it can support a weak grid instead of only following it. That matters as India adds more solar and wind.

How many containers does one block need?

With 5.015 MWh containers, it's about 910 for the 4.56 GWh block and 1,356 for the 6.80 GWh block on nameplate (Jingye estimate). Usable-energy guarantees and degradation push the real number higher.

Sizing a BESS bid for India?

Send us your block capacity, duration and usable-energy requirement, and we'll come back with a container configuration based on our 5.015 MWh unit.

Send your project requirements

Hebei Jingye New Energy Technology Co., Ltd, part of Jingye Group, makes liquid-cooled BESS containers, C&I energy storage cabinets, cell contact systems, commercial vehicle batteries and DC fast EV chargers.

LATEST BLOGS

Let’s Get Started on Your New Energy Journey.

Copyright @Hebei Jingye New Energy Technology Co., Ltd. All Rights Reserved | sitemap.xml

+86 0311 6736 8615

+86 0755 8666 6990

Cookie Consent

This website uses cookies to improve your browsing experience, analyze site traffic, and understand where our visitors come from. By continuing to use this site, you agree to our use of cookies.